Skylights, roofing and wiring

September 17th, 2007

Plenty of activity here today with the carpenters and the electricians working hard.

Last week the carpenters put in the skylights and started on the windows and roofing.

Installation of the metal roofing is continuing today.

We picked up my 1924 Glenwood gas cook stove from the Bryant Stove Works where it had been undergoing renovation.

And this weekend we retrieved the cat porch from the old house, a temporary treat for the cats.

David Gray and his son Kevin are working on the wiring.

Framing for interior walls

September 13th, 2007

Not all lumber deliveries went smoothly! Due to lack of turning space, trucks need to back in the 600′ driveway. Most of them make it, Gerald Fowler doing about 40 mph! Some are not so lucky.

Despite mishaps all the interior framing is now in place ready for the plumber and the electrician.

Cutting the holes for the windows

September 5th, 2007

At last, a start on installing the windows. And what a difference it makes! At my request, Gary and Mike started on the south side of the house.

The windows arrive

September 5th, 2007

Finally the end of the black hole is in sight! Once all the insulation was installed, the house lost much of its charm, the beautiful frame hidden and the interior quite dark. Yesterday the windows were delivered by Matthews Brothers of Belfast. Most of the windows and doors came from their bargain basement. One door, the slider and the skylights did not. A substantial amount of money was saved by careful shopping in the basement.

Porch, insulation, trim, chimney etc.

August 30th, 2007

It has been a busy few days with no free time to write posts.

The insulation arrived for the walls of the house.

There have been a few cold nights and autumn is definitely in the air, although it is hot and sunny today.

My passion flower vine is loving it here.

At night the loons and barred owls can be heard. In the evening the pileated woodpeckers make a terrific noise. It is wonderful to see them right by the house.

The masons have finished with the chimney, just the inside needs to be finished off. They gave me some lessons and I was able to build the brick pad for the wood stove to stand on.

Work has been progressing on the trim.

And the porch


Insulation is being installed on the south side of the house.

And the overhang on the south side is being finished off.

Starting the chimney and porch

August 28th, 2007

Yesterday the overhang was framed in and plywood installed to hold the metal roofing.

And the frame for the screen porch was started.

John Billings and his assistant Elmo started work on the chimney.

We are still hoping that the Trues Pond dam will be repaired this fall. In the meantime the canada geese are gathering.

Insulation

August 26th, 2007

The rigid insulation was delivered on Thursday. Rain on Friday stopped progress and then on Saturday Gary and his brothers braved the heat and humidity to install the roof panels.

V Match Pine

August 22nd, 2007

This week V-match pine has been installed for the ceiling and inner walls.

Contractors used in the Project

August 21st, 2007

These are contractors used in the project who I would highly recommend.

  • DRIVEWAY
      Lucas Construction
      Steve Lucas
      PO Box 159
      Searsmont, ME 04973
      207-342-5235
  • CONCRETE SLAB
      Joey Thornley, Jr
      622 South Mountain Valley Highway
      Montville, ME 04941
      207-589-4195
  • TIMBER FRAME
  • CHIMNEY
      John T. Billings
      1756 North Mountain Valley Highway,
      Montville, Maine 04941
      207-382-6145 cell 323-8426
  • WELL DRILLING
      E. A Cross and Sons
      Morrill, Maine
      207-342-5454
  • ELECTRICAL WORK
      Kenney and Gray, Inc.
      David Gray
      411 Cross Road
      Swanville, ME 04915
      207-338-4241 cell 322-9164
  • SOLAR ENERGY SYSTEM
      SolarTech Inc
      Bob Hussey
      50 Eustis Pkwy
      Waterville, ME 04901
      207-872-4531 Cell 207-649-0229

The roof trusses go up

August 21st, 2007

Yesterday afternoon the crane turned up to lift the trusses and in 1 hour and 20 minutes they were all in place. The crane was supplied by Northeast Equipment and Supply Company (722-3221) who were available at a reasonable cost.